Memories of August 2016 Shack Remodel

The entire remodel took place between August 13 and September 03.

General Shack Design

  • Two operating positions separated buy partitions with some sort of acoustic sound reduction. Operating tables/desks will be movable to provide for rear access for cabling
  • Meeting Area
  • Minimal solder/repair area for minor repairs
  • Relocation and consolidation of 2 meter repeater equipment

Construction Tasks

  • Removal of all equipment and items to a temporary storage POD
  • Dismantle and remove existing operating table and work bench
  • Replace all ceiling tiles
  • Paint all walls and add acoustic tiles in strategic places isolate sound
  • Install new flooring over existing floor
  • Consolidate 2m repeater equipment